Extension of Water Supply from Pre-Fabricated Health Post to Community in Kavre District
Objectives:
- To extend the water supply from Baluwa Health Post to the surrounding communities.
Key Activities:
- Technical Survey with Cost Estimation.
- Selection of Vendors, and agreement with service providers.
- Transportation of Materials and Equipment.
- TTo safeguard and extend water supply from pre-fabricated health post to community in Kavre District.
- Repair, Rehab or Construct Water Project for Baluwa Community, Kavre.
Major Achievements:
| Date |
Title |
| |
Construction of 10000 litre capacity ferrocement tank. |
| |
Construction of 4 public tap stands. |
| |
Backfilling of 1141 meter long pipeline that is laid under the ground has been done from the local community contribution. |
| |
For lifting water from deep boring to the ferrocement tank, 2 solar panels of Volta crystalline solar PV module 140 WP, 12V has been added and installed among the currently present solar panels. |
| |
654 people in 97 household in Khampur, Baluwa gained access to water supply from the taps on which water is supplied from ferrocement storage tank. |
| |
From the security point of view, for the preservation of storage tank, we have covered and surrounded the storage tank with barbed wire and angle poles. |